Implementation Programme

Applies to: All subscriptions

Purpose

Sequence a Complifly onboarding into ten stages, each with a deliverable, an owner and a gate — so that progress is measurable and a stage is never started before the one it depends on is genuinely finished.

Audience

Implementation consultants and the customer's project manager. Each stage page names its own specialist audience.

Prerequisites

  • Prerequisites worked, with the long-lead items already in motion
  • A named project manager on the customer side
  • Named owners for each stage

Steps

The ten stages

# Stage Owner Gate
1 Environment Preparation Infrastructure A verified installation
2 Master Data Setup Customer, with the consultant Data loaded and quality-checked
3 User Creation Administrator Users created and activated
4 Role Assignment Administrator, with the control owner Roles mapped and verified
5 GST Configuration Consultant, with the tax lead Registrations, routing and rates configured
6 e-Invoice Setup Consultant One document registered in the sandbox
7 e-Way Bill Setup Consultant, with logistics One bill generated in the sandbox
8 External System Connectivity Integration developer Documents flowing from the ERP
9 Validation Testing Customer, with the consultant Business acceptance
10 Go-Live Readiness Project manager Sign-off

The dependencies you cannot rearrange

  Prerequisites (started in week 0, runs throughout)
        |
        v
  1. Environment ------> 2. Master data ------> 3. Users ------> 4. Roles
        |                                                            |
        |                                                            v
        +--------------------------------> 5. GST configuration <----+
                                                  |
                                    +-------------+-------------+
                                    v                           v
                            6. e-Invoice                 7. e-Way Bill
                                    |                           |
                                    +-------------+-------------+
                                                  v
                                        8. Connectivity
                                                  |
                                                  v
                                        9. Validation testing
                                                  |
                                                  v
                                        10. Go-live readiness

Stages 6 and 7 can run in parallel. Stage 8 needs both, because an integration test that cannot reach a reference number proves only half the path.

Three rules that keep an implementation on track

Sandbox until stage 10. Every test before go-live uses sandbox provider credentials. A document sent with production credentials reaches the government, permanently consumes a real document number, and cannot be undone. Make the separation structural rather than a matter of care.

A stage is finished when its gate passes, not when its tasks are done. Tasks completing and a gate passing are different things, and the difference is where implementations quietly slip.

Long-lead items start in week zero. Provider credentials, statutory confirmation and licensing all depend on third parties. Technical work can be compressed; these cannot. See Commercial and Statutory Prerequisites.

An indicative shape

Week Focus
0 Kickoff. Start the commercial and statutory items immediately
1–2 Prerequisites; environment preparation
2–3 Installation and configuration; master data collection
3–4 Master data load; users and roles
4–5 GST configuration; module setup
5–7 Integration build and testing
7–8 Validation testing and business acceptance
8 Go-live readiness and sign-off
9 Go-live, with heightened support

Verify: This shape is indicative, not a commitment. Real duration depends on ERP complexity, master data quality and how early the long-lead items began. The most common cause of overrun is starting the commercial items late. Recorded as assumption C5 in the Assumptions Register.

Validation

The implementation is complete when:

Check Evidence
Every stage gate passed Signed, dated, with the owner named
One document processed end to end In production, on go-live day, watched
Users trained Each role can perform its work unaided
Operations handed over The customer's owner has the daily routine and knows who to contact
Monitoring live Configured and alerting, tested by firing an alert
Documentation handed over The customer can operate without the implementer
Support path known The customer knows how to raise a ticket before they need to

The last two are the point of the whole programme. An implementation that works only while the consultant is present is not finished.

Troubleshooting

Symptom Cause Action
Go-live approaching without provider credentials Commercial items started late Escalate commercially. No technical work substitutes
A stage keeps reopening Its gate was passed on tasks completed rather than outcomes Re-apply the gate honestly
Testing finds problems that should have been caught earlier Edge cases not supplied during data collection Request them by name; see Information Checklist
The ERP team is unavailable at stage 8 Effort never allocated Escalate. This is a scoping failure, not a technical one
A test document reached the government Production credentials in a non-production environment Treat as an incident. The number is permanently consumed
Everything works until the consultant leaves Handover treated as a formality Handover is a stage gate. The customer must demonstrate, not receive